How Long It Takes to Get a Farm Shed Built

With a grant, allow about 15 months from the planning application to stock in the shed. Planning takes about two months. TAMS approval takes six to twelve. The build itself is the short part: a few months from foundations to gates. Without a grant, a shed that is exempt from planning can be up in a season. To house cattle next winter, start the paperwork this winter.

Each stage, how long it takes, and what holds people up.

Free, no obligation. One local company prices it, not five.

  • 15 monthsplanning application to stock in, with a grant
  • 2 monthsfor a planning decision
  • 6 to 12 monthsfor TAMS approval

The stages

StageHow longWhat you need
Design and drawingsA few weeksA consultant, and a decision on size and layout
Planning permission or a Section 5 declarationAbout two monthsDrawings, site map, the fee
Grant applicationIn an open trancheThe planning decision, drawings, the spec
Grant approvalSix to twelve monthsPatience. No work may start
Site work and concreteWeeksDry ground helps
Steel, sheeting, fit-outWeeksSlats and steel ordered in time
Grant claimAfter completionInvoices, certificates, photos

What holds a shed up

  • Starting the planning late. The grant application can't go in without it.
  • Missing a tranche. Applications are taken in rounds and ranked.
  • Further information requests from the council, which stop the planning clock.
  • Wet ground. A tank dug in November is a different job from one dug in June.
  • Lead times. Slats, steel and builders are all booked ahead in spring and summer.

Working back from next winter

Cattle are housed from October or November. To have a grant-aided shed ready, the builder needs to start by early summer, so approval has to be in hand by spring, so the application has to be in the winter before, with planning already granted.

If that date has passed, the choices are to build without the grant, or to plan properly for the winter after.

Every guide, calculator and county page

Jump straight to any specification guide, our interactive calculator, the technical glossary or your county page.

Price your shed

Four taps: what the shed is for, how many bays, new or extension, grant or no grant. You see the likely shed and our price for it. Your number is only asked for at the end, if you want one farm shed builder that covers your county to ring you.

What is the shed for?

Pick the nearest. They'll ask the rest.

Privacy notice

Questions people ask

How long does planning take for a farm shed?

About two months for a decision, if the council doesn't ask for more information.

How long does TAMS approval take?

Six to twelve months.

How long does the building take?

A few months for a typical shed, once work starts.

Can I start while I wait for the grant?

No. Work started before approval isn't grant-aided.

What is the fastest way to get a shed?

A shed that is exempt from planning, built without a grant, by a builder with a free slot.

Get a price for your farm shed

One farm shed builder that covers your county. Free, no obligation. Nothing is booked until you say yes.